In a 1-page Word document, consider the following activities and their durations. The original project schedule, using early activity starts, is shown below. ActivityTaskPredecessorsDurationActivity CostASign ContractNone5 days$5,000BDesign SurveyA3 days$1,500CIdentify AudienceA7 days$1,000DRun SurveyB, C30 days$6,000EAnalyze ResultsD5 days$3,000FCreate PresentationE5 days$1,000GPresent to ClientE, F2 days$3,000 Reconfigure the chart above into a critical path diagram for project scheduling similar […]