Answered>Order 425

9) The annual demand for a product has been projected at 2,000 units. This demand is assumed to be constant throughout the year. The ordering cost is $20 per order, and the holding cost is 20 percent of the purchase cost. The purchase cost is $40 per unit. There are 250 working days per year. Whenever an order is placed, it is known that the entire order will arrive on a truck in 6 days. Currently, the company is ordering 500 units each time an order is placed. What level of safety stock would give a reorder point of 60 units?

A) 10

B) 14

C) 18

D) 12

E) 22

 
"Not answered?"
Get the Answer