Determine the critical path and the time it will take to complete the project. 

A-Pack up factory- Predecessor-no-Duration-3 days

B-Find new location-Predecessor-no-Duration-4 days

C-Hire moving company-Predecessor-no-Duration-1 day

D-Arrange shipments with suppliers-Predecessor-no-Duration-1 day

E-Load and move to new location-Predecessor-A,B,C- Duration 2 days

F-Set up new factory-Predecessor-A,C,E-Duration 3 days

G-Receive raw materials-Predecessor-E,D-Duration-2 Days

H-Produce product-Predecessor-F,G-Duration- 3 Days

I-Pack and Ship to customer-Predecessor-H-Duration- 1 day

 