Determine the critical path and the time it will take to complete the project.
A-Pack up factory- Predecessor-no-Duration-3 days
B-Find new location-Predecessor-no-Duration-4 days
C-Hire moving company-Predecessor-no-Duration-1 day
D-Arrange shipments with suppliers-Predecessor-no-Duration-1 day
E-Load and move to new location-Predecessor-A,B,C- Duration 2 days
F-Set up new factory-Predecessor-A,C,E-Duration 3 days
G-Receive raw materials-Predecessor-E,D-Duration-2 Days
H-Produce product-Predecessor-F,G-Duration- 3 Days
I-Pack and Ship to customer-Predecessor-H-Duration- 1 day