Activity IDActivityPredecessorDuration (Minutes)DDisarm the exterior alarm-20JSCrack the jewelry safeD15CJClean out the jewelry safeJS9OADisarm the office alarmD7OSCrack the office safeOA8COClean out the office safeOS4RRun to the car and leaveCJ , CO4A. Draw a PERT/CPM diagram (use AON) to represent the schedule. Calculate the early start, early finish, late start, late finish, and slack time for each activity. Use the drawing feature in MS Word to answerB. After determining a schedule, you found some accomplices. You can defeat any alarm system, your first accomplice specializes in cracking safes, and your third accomplice is available to help carry the goods and drive the car. Redraw the network diagram taking into account the resources and calculate the critical chain.

Activity IDActivityPredecessorDuration (Minutes)

DDisarm the exterior alarm-20

JSCrack the jewelry safeD15

CJClean out the jewelry safeJS9

OADisarm the office alarmD7

OSCrack the office safeOA8

COClean out the office safeOS4

RRun to the car and leaveCJ , CO4

A. Draw a PERT/CPM diagram (use AON) to represent the schedule. Calculate the early start, early finish, late start, late finish, and slack time for each activity. Use the drawing feature in MS Word to answer

B. After determining a schedule, you found some accomplices. You can defeat any alarm system, your first accomplice specializes in cracking safes, and your third accomplice is available to help carry the goods and drive the car. Redraw the network diagram taking into account the resources and calculate the critical chain.

 
"Looking for a Similar Assignment? Get Expert Help at an Amazing Discount!"

Comments are closed.

Hi there! Click one of our representatives below and we will get back to you as soon as possible.

Chat with us on WhatsApp