Activity IDActivityPredecessorDuration (Minutes)DDisarm the exterior alarm-20JSCrack the jewelry safeD15CJClean out the jewelry safeJS9OADisarm the office alarmD7OSCrack the office safeOA8COClean out the office safeOS4RRun to the car and leaveCJ , CO4A. Draw a PERT/CPM diagram (use AON) to represent the schedule. Calculate the early start, early finish, late start, late finish, and slack time for each activity. Use the drawing feature in MS Word to answerB. After determining a schedule, you found some accomplices. You can defeat any alarm system, your first accomplice specializes in cracking safes, and your third accomplice is available to help carry the goods and drive the car. Redraw the network diagram taking into account the resources and calculate the critical chain.
Activity IDActivityPredecessorDuration (Minutes)
DDisarm the exterior alarm-20
JSCrack the jewelry safeD15
CJClean out the jewelry safeJS9
OADisarm the office alarmD7
OSCrack the office safeOA8
COClean out the office safeOS4
RRun to the car and leaveCJ , CO4
A. Draw a PERT/CPM diagram (use AON) to represent the schedule. Calculate the early start, early finish, late start, late finish, and slack time for each activity. Use the drawing feature in MS Word to answer
B. After determining a schedule, you found some accomplices. You can defeat any alarm system, your first accomplice specializes in cracking safes, and your third accomplice is available to help carry the goods and drive the car. Redraw the network diagram taking into account the resources and calculate the critical chain.